Feb. 28-March 14
Feb 28: This past week we finished the bearing CMU masonry walls. Just this week, we successfully started Structural steel for the addition. The steel sequence will last from 2/26 and end on 3/15. After the steel sequence, we will then start framing the exterior stud walls. We will be doing something exciting on Monday. Pepper Construction has offered to paint one of these long beams and allow our students and staff to sign the beam with a Sharpie. We'll take lots of pictures! Check out some cool pix from the past. It is really shaping quickly.