Feb. 3-17

Feb. 3: We are making steady progress with our construction project. As you can see from the photos, we have the footings poured and the steel rebar is being installed for the foundation. This week the Ranch View community will see more truck traffic due to our major work for the week of February 3rd- Stone backfill. Coming in the next few weeks will be the masontry bearing and fire wall and exterior wall framing.  We will also be having Construction Assemblies with our students on Tuesday, February 4th. This is an opportunity for our students to learn more about the project from our team of architects from Healy Bender and our project management team from Pepper Construction. We are looking forward to hearing from the groups that helped create the vision and the people making that vision come to life.